Procedure For Reno 2018 Monitor ATSI Test
- Enter Reno 2018 Monitor data into Monitor Info (serial number, etc.)
- On the PCMT-8000 go to “Test Setup” Test Standard Caltrans Model 2010, Monitor Type 18 Channel, Test type Certification, and Test Lap One. (see below)
- In the MonitorKey software set the following:
- Option dip switch: 7 (2010) “on” (all others “off)
- DUAL ENABLE dip switch: all “on” (DUAL ENABLE on for all channels)
- RED FAIL dip switch: all “on” (SSM on for all channels)
- WD Enable: “on”
- Insert “Regular Test Card” all diodes are soldered in
- Start test (make sure you Reset Monitor for 5 sec after setting switches)
- Tester will “beep” when complete